November 9, 1945. Howard Street Pavement and Sidewalk Project. This view was taken at the intersection of Hayward Street looking westerly. Note the new concrete sidewalk on north side and new integral concrete curbs and gutters on both sides of pavement. The Hot Plant Mix Asphalt Wearing Surface was just bieng completed when this picture was taken. Grading between curb and sidewalk on North Side and in back of curb on South side was completed the following day after picture was taken. The 2 inch asphalt wearing surface was placed on a 3 inch penetration macadam with an 8 inch telford stone base. Drainage tile was laid the entire length of the street on the rear of the curbs on either side and in the center line of the street. All tile was drained with catch basins and manholes.