December 5, 1945. For dated photo see also Burlington Streets: Lakeside Ave mcalA05F11i02 City of Burlington, Vermont, Street Department Lakeside Ave. Pavement Base Construction This view was taken from a point near the intersection of Central Ave. looking easterly toward the underpass. The new factory building just completed for the Blodgett Co. is shown with parking area base recently constructed between the street line and the building. Note the asphalt emulsion stabilized base which was mixed the previous day before taking this picture. Cold weather and frost conditions had frozen the base mixture on the left half of the street but the job was continued on the north half in spite of the low temperatures as the street had to be put in condition to receive traffic for the winter, this street being on a regular bus line. The job was continued by placing a 2 inch layer of crushed stone on this stabilized base and penetrating the same with asphalt emulsion and covering with concrete sand as a "blotter" for the winter and then opened to traffic. This project will be continued to completion in the spring by constructing an integral concrete curb and gutter on the south side of a 2 inch hot plant mix wearing surface over the entire pavement area. Note the asphalt distributor applying emulsion and the tractor and harrow mixing the base.